Arida Solar (Hybrid) πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / nevada /
Dates
First heard 2022-01
Construction start
Operation start
Estimated start 2027-12
Construction time
Capacity in MWh
740
πŸ“ This is an estimate
Maximum Power in MW
370
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ 326FW 8me LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.28470862756772+-114.82195337753002
Coordinates
41.28470862756772, -114.82195337753002
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
576 / 63841

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2022-01 report):

Plant Name / State
Arida Solar (Hybrid) / NV
go live / power
2027-12 / 370MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
63841 / BESS
Entity name / entity id
326FW 8me LLC / 63520
Changes:
2024-02
date: 2027-06 -> 2027-12 delayed by 6 months
2023-12
date: 2024-10 -> 2027-06 delayed by 32 months
mw: 185 -> 370