Zeta Solar & Storage πππ
Status
planning
Country / State / Closest City
πΊπΈ usa / california /
Dates
First heard |
2024-07 |
Construction start |
|
Operation start |
|
Estimated start |
2027-06 |
Construction time |
|
Capacity in MWh
150
π This is an estimate
Maximum Power in MW
75
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Zeta Solar, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.30551484072874+-121.1672095329819
Coordinates
41.30551484072874, -121.1672095329819
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1483 / 67676
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2024-07
report):
Plant Name / State
Zeta Solar & Storage / CA
go live / power
2027-06 / 75MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
67676 / GEN02
Entity name / entity id
Zeta Solar, LLC / 66318
Changes: