AES West Oahu Solar Hybrid πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / hawaii /
Dates
First heard |
2021-06 |
Construction start |
2022-09 |
Operation start |
2024-03 |
Estimated start |
2022-09 |
Construction time |
18 months -> 1 MWh/m
|
Capacity in MWh
24
π This is an estimate
Maximum Power in MW
12
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ AES Distributed Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:19.54447929522626+-155.30620467944766
Coordinates
19.54447929522626, -155.30620467944766
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
219 / 64656
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2021-06
report):
Plant Name / State
AES West Oahu Solar Hybrid / HI
go live / power
2024-03 / 12MW
status / status verbose
operation / operation
Plant id / generator id
64656 / UHBES
Entity name / entity id
AES Distributed Energy / 61012
Changes:
2024-05
status: construction -> operation πΎ π πΈ
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2024-04
date: 2024-02 -> 2024-03 delayed by
1 month
2024-03
date: 2024-01 -> 2024-02 delayed by
1 month
2023-11
date: 2023-09 -> 2024-01 delayed by
4 months
2023-05
date: 2023-06 -> 2023-09 delayed by
3 months
2023-03
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2022-10
date: 2023-01 -> 2023-06 delayed by
5 months
2022-09
status: planning -> construction ποΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2022-06
date: 2022-09 -> 2023-01 delayed by
4 months