Pike Solar Hybrid πŸ“πŸ“ŠπŸ“

Status
cancelled
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / colorado /
Dates
First heard 2021-01
Construction start
Operation start
Estimated start 2023-12
Month disappeared 2023-03
Construction time
Capacity in MWh
50
πŸ“ This is an estimate
Maximum Power in MW
25
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Pike Solar LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.75811546015096+-102.75746524325749
Coordinates
40.75811546015096, -102.75746524325749
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
206 / 64212

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2023-02 report (Project first appeared in the 2021-01 report):

Plant Name / State
Pike Solar Hybrid / CO
go live / power
2023-12 / 25MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
64212 / PSBES
Entity name / entity id
Pike Solar LLC / 63821
Changes:



2023-03 This project disappeared in the 2023-03 report.
That's why the status was set to cancelled