VESI Pomona πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2023-03
Construction start
Operation start 2023-08
Estimated start 2023-06
Construction time
Capacity in MWh
40
πŸ“ This is an estimate
Maximum Power in MW
20
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ VESI Pomona Energy Storage, Inc. /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.122677+-121.180049
Coordinates
41.122677, -121.180049
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
960 / 50300

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2023-03 report):

Plant Name / State
VESI Pomona / CA
go live / power
2023-08 / 20MW
status / status verbose
operation / operation
Plant id / generator id
50300 / BESS2
Entity name / entity id
VESI Pomona Energy Storage, Inc. / 54736
Changes:
2023-10
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
date: 2023-10 -> 2023-08 accelerated by 2 months
2023-07
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
2023-06
date: 2023-06 -> 2023-10 delayed by 4 months
2023-05
date: 2023-05 -> 2023-06 delayed by 1 month