Saint Energy Storage II LLC πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / arizona /
Dates
First heard |
2023-07 |
Construction start |
|
Operation start |
2023-09 |
Estimated start |
2023-07 |
Construction time |
|
Capacity in MWh
200
π This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Saint Energy Storage II LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:36.478429+-109.905254
Coordinates
36.478429, -109.905254
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1010 / 66716
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-02
report (Project first appeared in the
2023-07
report):
Plant Name / State
Saint Energy Storage II LLC / AZ
go live / power
2023-09 / 100MW
status / status verbose
operation / operation
Plant id / generator id
66716 / SB123
Entity name / entity id
Saint Energy Storage II LLC / 65727
Changes:
2023-11
status: construction -> operation πΎ π πΈ
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2023-10
date: 2023-08 -> 2023-09 delayed by
1 month
2023-09
date: 2023-07 -> 2023-08 delayed by
1 month