Lower Rio Energy Storage πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2025-02
Construction start
Operation start
Estimated start 2025-06
Construction time
Capacity in MWh
120
πŸ“ This is an estimate
Maximum Power in MW
60
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ VESI 38 LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.454054+-95.333438
Coordinates
33.454054, -95.333438
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1730 / 68496

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2025-04 report (Project first appeared in the 2025-02 report):

Plant Name / State
Lower Rio Energy Storage / TX
go live / power
2025-06 / 60MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
68496 / LOWR1
Entity name / entity id
VESI 38 LLC / 66850