Elevate Pier S πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2023-08
Construction start
Operation start
Estimated start 2026-06
Construction time
Capacity in MWh
140
πŸ“ This is an estimate
Maximum Power in MW
70
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Pier S Energy Storage LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.98395968045898+-121.10912098932751
Coordinates
40.98395968045898, -121.10912098932751
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1038 / 66787

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2023-08 report):

Plant Name / State
Elevate Pier S / CA
go live / power
2026-06 / 70MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
66787 / ELVPS
Entity name / entity id
Pier S Energy Storage LLC / 65764
Changes: