Sagebrush ESS πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2022-09
Construction start 2022-11
Operation start 2023-05
Estimated start
Construction time 6 months -> 26 MWh/m
Capacity in MWh
160
πŸ“ This is an estimate
Maximum Power in MW
80
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Terra-Gen Operating Co-BESS 2 /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.86398962756772+-121.21599637753002
Coordinates
40.86398962756772, -121.21599637753002
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
776 / 65933

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2022-09 report):

Plant Name / State
Sagebrush ESS / CA
go live / power
2023-05 / 80MW
status / status verbose
operation / operation
Plant id / generator id
65933 / 1
Entity name / entity id
Terra-Gen Operating Co-BESS 2 / 65552
Changes:
2023-07
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2023-05
entity id: 64287 -> 65552
entity name: Terra-Gen Operating Co-BESS -> Terra-Gen Operating Co-BESS 2
2023-04
entity id: 65106 -> 64287
entity name: Sagebrush ESS, LLC -> Terra-Gen Operating Co-BESS
date: 2023-03 -> 2023-05 delayed by 2 months
2023-02
date: 2023-01 -> 2023-03 delayed by 2 months
2022-11
status: planning -> construction πŸ—οΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (V) Under construction, more than 50 percent complete