Sanborn BESS 3 πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / california /
Dates
First heard |
2022-06 |
Construction start |
|
Operation start |
2023-10 |
Estimated start |
2023-05 |
Construction time |
|
Capacity in MWh
338
π This is an estimate
Maximum Power in MW
169
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Terra-Gen Operating Co-BESS /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.832677000000004+-121.300049
Coordinates
40.832677000000004, -121.300049
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
695 / 65672
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-02
report (Project first appeared in the
2022-06
report):
Plant Name / State
Sanborn BESS 3 / CA
go live / power
2023-10 / 169MW
status / status verbose
operation / operation
Plant id / generator id
65672 / BESS
Entity name / entity id
Terra-Gen Operating Co-BESS / 64287
Changes:
2023-12
status: construction -> operation πΎ π πΈ
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
2023-11
date: 2023-09 -> 2023-10 delayed by
1 month
2023-09
date: 2023-08 -> 2023-09 delayed by
1 month
2023-04
mw: 175 -> 169
2022-12
date: 2023-05 -> 2023-08 delayed by
3 months