Chisholm Grid Energy Storage System πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2020-09 |
Construction start |
2020-10 |
Operation start |
2021-10 |
Estimated start |
2021-09 |
Construction time |
12 months -> 16 MWh/m
|
Capacity in MWh
200
π This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Chisholm Grid, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.572170481178745+-95.1876213531653
Coordinates
33.572170481178745, -95.1876213531653
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
243 / 63737
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2022-02
report (Project first appeared in the
2020-09
report):
Plant Name / State
Chisholm Grid Energy Storage System / TX
go live / power
2021-10 / 100MW
status / status verbose
operation / operation
Plant id / generator id
63737 / CHS01
Entity name / entity id
Chisholm Grid, LLC / 63430
Changes:
2021-12
status: construction -> operation πΎ π πΈ
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
2021-11
date: 2021-09 -> 2021-10 delayed by
1 month
2021-09
date: 2021-07 -> 2021-09 delayed by
2 months
2021-08
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
2021-06
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2021-02
entity name: Astral Electricity, LLC -> Chisholm Grid, LLC
2020-10
status: planning -> construction ποΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete