Chisholm Grid Energy Storage System πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2020-09
Construction start 2020-10
Operation start 2021-10
Estimated start
Construction time 12 months -> 16 MWh/m
Capacity in MWh
200
πŸ“ This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Chisholm Grid, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.572170481178745+-95.1876213531653
Coordinates
33.572170481178745, -95.1876213531653
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
243 / 63737

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2022-02 report (Project first appeared in the 2020-09 report):

Plant Name / State
Chisholm Grid Energy Storage System / TX
go live / power
2021-10 / 100MW
status / status verbose
operation / operation
Plant id / generator id
63737 / CHS01
Entity name / entity id
Chisholm Grid, LLC / 63430
Changes:
2021-12
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
2021-11
date: 2021-09 -> 2021-10 delayed by 1 month
2021-09
date: 2021-07 -> 2021-09 delayed by 2 months
2021-08
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
2021-06
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2021-02
entity name: Astral Electricity, LLC -> Chisholm Grid, LLC
2020-10
status: planning -> construction πŸ—οΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete