Bowling Green Energy Storage Project πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / ohio /
Dates
First heard |
2022-09 |
Construction start |
|
Operation start |
2023-05 |
Estimated start |
2022-10 |
Construction time |
|
Capacity in MWh
24
π This is an estimate
Maximum Power in MW
12
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ VESI 21 LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.44479209297624+-80.98205271403428
Coordinates
41.44479209297624, -80.98205271403428
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
781 / 65951
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-02
report (Project first appeared in the
2022-09
report):
Plant Name / State
Bowling Green Energy Storage Project / OH
go live / power
2023-05 / 12MW
status / status verbose
operation / operation
Plant id / generator id
65951 / BG1
Entity name / entity id
VESI 21 LLC / 65129
Changes:
2023-07
status: construction -> operation πΎ π πΈ
status_verbose: (V) Under construction, more than 50 percent complete -> operation
date: 2023-06 -> 2023-05 accelerated by
1 month
2023-06
date: 2023-04 -> 2023-06 delayed by
2 months
2023-05
date: 2023-03 -> 2023-04 delayed by
1 month
2023-04
date: 2023-02 -> 2023-03 delayed by
1 month
2023-03
date: 2023-01 -> 2023-02 delayed by
1 month
2023-02
date: 2023-02 -> 2023-01 accelerated by
1 month
2022-11
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
date: 2022-10 -> 2023-02 delayed by
4 months