Scarlet II Hybrid πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2023-10
Construction start 2024-07
Operation start
Estimated start 2024-12
Construction time
Capacity in MWh
300
πŸ“ This is an estimate
Maximum Power in MW
150
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ EDPR Scarlet II LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.88482600365377+-121.12724013582601
Coordinates
40.88482600365377, -121.12724013582601
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1177 / 66951

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2023-10 report):

Plant Name / State
Scarlet II Hybrid / CA
go live / power
2024-12 / 150MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
66951 / GEN04
Entity name / entity id
EDPR Scarlet II LLC / 65859
Changes:
2024-07
status: planning -> construction πŸ—οΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2024-01
date: 2024-10 -> 2024-12 delayed by 2 months
2023-12
date: 2024-06 -> 2024-10 delayed by 4 months