Arrowleaf Solar and Storage πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2024-08
Construction start 2025-01
Operation start
Estimated start 2025-04
Construction time
Capacity in MWh
70
πŸ“ This is an estimate
Maximum Power in MW
35
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ ORNI 30 LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.04295061545127+-121.05467641879585
Coordinates
41.04295061545127, -121.05467641879585
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1539 / 67850

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2025-01 report (Project first appeared in the 2024-08 report):

Plant Name / State
Arrowleaf Solar and Storage / CA
go live / power
2025-04 / 35MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
67850 / ALBS1
Entity name / entity id
ORNI 30 LLC / 66422
Changes:
2025-01
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2024-10
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (T) Regulatory approvals received. Not under construction