Paleo πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2022-04
Construction start 2023-03
Operation start
Estimated start 2024-06
Construction time
Capacity in MWh
400
πŸ“ This is an estimate
Maximum Power in MW
200
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Engie North America /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.70808533623373+-95.45800256921983
Coordinates
33.70808533623373, -95.45800256921983
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
687 / 65491

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2022-04 report):

Plant Name / State
Paleo / TX
go live / power
2024-06 / 200MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
65491 / PALEO
Entity name / entity id
Engie North America / 56201
Changes:
2024-06
date: 2024-04 -> 2024-06 delayed by 2 months
2024-05
date: 2024-03 -> 2024-04 delayed by 1 month
2024-03
entity id: 63883 -> 56201
entity name: Broad Reach Power -> Engie North America
2023-10
date: 2024-02 -> 2024-03 delayed by 1 month
2023-04
date: 2023-12 -> 2024-02 delayed by 2 months
2023-03
status: planning -> construction πŸ—οΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
date: 2023-06 -> 2023-12 delayed by 6 months