Saticoy πŸ“ŠπŸ‘€

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california / oxnard / los angeles
Dates
First heard 2020-09
Construction start 2020-11
Operation start 2021-04
Estimated start
Construction time 5 months -> 80 MWh/m
Capacity in MWh
400
Maximum Power in MW
100
Manufacturer
tesla
Type / Number of Packs / Cells
megapack / 142 /
Customer / Owner / Developer
Arevon / Ventura Energy Storage, LLC /
Use case
peaker plant replacement
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:34.25773+-119.158534
Coordinates
34.25773, -119.158534
βœ… Coords are exact (+/- 50m)
Notes

Project website
Sources
https://electrek.co/2021/06/30/tesla-megapacks-power-on-battery-replacing-gas-peaker-plant-california/
https://www.prnewswire.com/news-releases/arevon-powers-oxnard-forward-with-saticoy-battery-storage-project-301321788.html
https://arevonenergy.com/location/saticoy/
Internal / External id
3 / 63891

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2022-02 report (Project first appeared in the 2020-09 report):

Plant Name / State
Saticoy / CA
go live / power
2021-04 / 100MW
status / status verbose
operation / operation
Plant id / generator id
63891 / SATCY
Entity name / entity id
Ventura Energy Storage, LLC / 63550
Changes:
2021-06
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
date: 2021-05 -> 2021-04 accelerated by 1 month
2021-04
date: 2021-04 -> 2021-05 delayed by 1 month
2020-11
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete