Sawtooth Solar πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / arizona /
Dates
First heard 2025-06
Construction start
Operation start
Estimated start 2028-06
Construction time
Capacity in MWh
500
πŸ“ This is an estimate
Maximum Power in MW
250
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ EDF Renewables Development, Inc. /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:36.62890616095374+-109.7759259430736
Coordinates
36.62890616095374, -109.7759259430736
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1763 / 68883

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2025-07 report (Project first appeared in the 2025-06 report):

Plant Name / State
Sawtooth Solar / AZ
go live / power
2028-06 / 250MW
status / status verbose
planning / (L) Regulatory approvals pending. Not under construction
Plant id / generator id
68883 / STBA
Entity name / entity id
EDF Renewables Development, Inc. / 64452