Kuna BESS πππ
Status
planning
Country / State / Closest City
πΊπΈ usa / idaho /
Dates
First heard |
2024-06 |
Construction start |
|
Operation start |
|
Estimated start |
2025-06 |
Construction time |
|
Capacity in MWh
300
π This is an estimate
Maximum Power in MW
150
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Kuna BESS, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:44.453334+-112.673786
Coordinates
44.453334, -112.673786
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1345 / 67549
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2024-06
report):
Plant Name / State
Kuna BESS / ID
go live / power
2025-06 / 150MW
status / status verbose
planning / (T) Regulatory approvals received. Not under construction
Plant id / generator id
67549 / 1
Entity name / entity id
Kuna BESS, LLC / 66265
Changes: