Great Kiskadee Storage πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2024-12
Construction start
Operation start
Estimated start 2025-01
Construction time
Capacity in MWh
200
πŸ“ This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Great Kiskadee Storage, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.41643574385328+-95.32521508763999
Coordinates
33.41643574385328, -95.32521508763999
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1612 / 68189

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2025-01 report (Project first appeared in the 2024-12 report):

Plant Name / State
Great Kiskadee Storage / TX
go live / power
2025-01 / 100MW
status / status verbose
construction / (TS) Construction complete, but not yet in commercial operation
Plant id / generator id
68189 / GKDBS
Entity name / entity id
Great Kiskadee Storage, LLC / 66623
Changes:
2025-01
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation