Fifth Standard Solar PV, LLC (Hybrid) πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / california /
Dates
First heard |
2021-01 |
Construction start |
2022-11 |
Operation start |
2023-09 |
Estimated start |
2022-09 |
Construction time |
10 months -> 23 MWh/m
|
Capacity in MWh
234
π This is an estimate
Maximum Power in MW
117
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ RWE Renewables Americas, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.296661434678576+-121.53951803033499
Coordinates
41.296661434678576, -121.53951803033499
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
168 / 64197
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-02
report (Project first appeared in the
2021-01
report):
Plant Name / State
Fifth Standard Solar PV, LLC (Hybrid) / CA
go live / power
2023-09 / 117MW
status / status verbose
operation / operation
Plant id / generator id
64197 / FTHSB
Entity name / entity id
RWE Renewables Americas, LLC / 56215
Changes:
2023-11
status: construction -> operation πΎ π πΈ
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
2023-10
date: 2023-08 -> 2023-09 delayed by
1 month
2023-07
date: 2023-10 -> 2023-08 accelerated by
2 months
2023-05
entity name: RWE Renewables Americas LLC -> RWE Renewables Americas, LLC
2023-04
date: 2023-09 -> 2023-10 delayed by
1 month
2022-11
status: planning -> construction ποΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2022-08
date: 2022-12 -> 2023-09 delayed by
9 months
2021-11
date: 2022-09 -> 2022-12 delayed by
3 months
2021-03
date: 2022-12 -> 2022-09 accelerated by
3 months
2021-02
plant name: Fifth Standard Solar PV, LLC -> Fifth Standard Solar PV, LLC (Hybrid)