Pome BESS πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2024-04
Construction start
Operation start
Estimated start 2025-03
Construction time
Capacity in MWh
200
πŸ“ This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ MN8 Energy LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.94007414887133+-121.24071773708002
Coordinates
40.94007414887133, -121.24071773708002
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1336 / 67299

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2025-04 report (Project first appeared in the 2024-04 report):

Plant Name / State
Pome BESS / CA
go live / power
2025-03 / 100MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
67299 / 10101
Entity name / entity id
MN8 Energy LLC / 61944
Changes:
2025-04
status_verbose: (V) Under construction, more than 50 percent complete -> (U) Under construction, less than or equal to 50 percent complete
2025-03
entity id: 66165 -> 61944
entity name: IOWN Renewable -> MN8 Energy LLC
2025-02
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2024-11
date: 2024-12 -> 2025-03 delayed by 3 months
2024-08
date: 2024-09 -> 2024-12 delayed by 3 months
2024-06
date: 2024-11 -> 2024-09 accelerated by 2 months