Mordor ES1 πππ
Status
construction
Country / State / Closest City
πΊπΈ usa / california /
Dates
First heard |
2024-08 |
Construction start |
|
Operation start |
|
Estimated start |
2025-04 |
Construction time |
|
Capacity in MWh
50
π This is an estimate
Maximum Power in MW
25
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Mordor ES1 LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.122677+-121.220049
Coordinates
41.122677, -121.220049
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1540 / 67828
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2025-01
report (Project first appeared in the
2024-08
report):
Plant Name / State
Mordor ES1 / CA
go live / power
2025-04 / 25MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
67828 / MES1
Entity name / entity id
Mordor ES1 LLC / 66405
Changes:
2024-10
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete