🇩🇪 DE MaStR data (>10MW)

Latest DE MaStR report from 2022-12
operation 🏗️ 💻
Projects count 27 0 6
Total 🔋 battery power in GW 0.5 0.0 0.2
Total 🔋 battery capacity in GWh 0.5 0.0 0.2
🏗️ = construction; 💻 = planning

Monthly big battery changes from DE MaStR reports


2022-12

New projects (5):
60 MW - planning - thuringia - SMAREG4 Wartburgspeicher Eisenach - SEE954649497618
20 MW - operation - bavaria - Batterie Diespeck - SEE995000682977
20 MW - operation - bavaria - Batterie Iphofen - SEE934353123843
13 MW - operation - saxony - Bad Düben Battery Storage - SEE961989517128
13 MW - operation - saxony-anhalt - Elsteraue Battery Storage - SEE932907515472

Updated projects (3):

48 MW - operation - schleswig-holstein - BESS Jardelund - SEE999790559914
  NetzbetreiberpruefungDatum: 2021-02-12 -> 2022-11-11
12 MW - operation - bavaria - 70000000.00 - SEE940316838242
  NetzbetreiberpruefungDatum: 2022-07-26 -> 2022-11-10
10 MW - operation - thuringia - Batterie Breitenworbis - SEE977720016904
  NetzbetreiberpruefungDatum: 2022-01-13 -> 2022-11-09

2022-08

New projects (0):

Disappeared projects (1):
13 MW - planning - baden-wuerttemberg - Im Buckeberg 62 Stromspeicher - SEE946919525862

Updated projects (4):

17 MW - operation - nrw - Q_ESS_Elverlingsen - SEE966091400436
  NetzbetreiberpruefungStatus: 0 -> 1
  NetzbetreiberpruefungDatum: 2021-05-26 -> 2022-06-01
12 MW - operation - bavaria - 70000000.00 - SEE940316838242
  DatumLetzteAktualisierung: 2021-12-16T16:44:50.4826401 -> 2022-07-25T12:53:41.6823712
  NetzbetreiberpruefungStatus: 0 -> 1
  NetzbetreiberpruefungDatum: 2022-03-31 -> 2022-07-26
  owner: ENGIE Deutschland GmbH Geschäftsbereich Energy Services -> ENGIE Deutschland GmbH
10 MW - operation - brandenburg - RRKW Feldheim - SEE976927444749
  DatumLetzteAktualisierung: 2020-01-08T14:16:54.1030683 -> 2022-05-04T10:40:15.0620181
  NetzbetreiberpruefungDatum: 2022-03-03 -> 2022-07-07
10 MW - operation - thuringia - SMAREG 1 - SEE931375347240
  NetzbetreiberpruefungStatus: 0 -> 1
  NetzbetreiberpruefungDatum: 2021-08-11 -> 2022-05-20

2022-05

New projects (1):
10 MW - operation - thuringia - Batterie Eisenach - SEE982806373970

Updated projects (6):

18 MW - operation - bremen - Hybridregelkraftwerk - SEE913862454280
  DatumLetzteAktualisierung: 2020-07-08T12:59:43.6915182 -> 2022-02-03T10:32:33.3178725
  Kraftwerksnummer_nv: 1 -> 0
13 MW - planning - schleswig-holstein - Büttel Speicher - SEE984446277410
  DatumLetzteAktualisierung: 2020-08-26T09:44:58.0831462 -> 2022-01-27T13:56:34.4520410
12 MW - operation - bavaria - 70000000.00 - SEE940316838242
  NetzbetreiberpruefungStatus: 1 -> 0
  NetzbetreiberpruefungDatum: 2021-12-16 -> 2022-03-31
  owner: ENGIE Deutschland GmbH -> ENGIE Deutschland GmbH Geschäftsbereich Energy Services
11 MW - operation - lower saxony - Energiewende-Speicher - SEE935506652999
  DatumLetzteAktualisierung: 2020-09-23T14:27:02.7620630 -> 2022-03-03T11:54:48.0427347
  NetzbetreiberpruefungStatus: 0 -> 1
  NetzbetreiberpruefungDatum: 2021-12-28 -> 2022-04-27
  Inbetriebnahmedatum: 2018-08-02 -> 2018-05-31
10 MW - planning - mecklenburg-vorpommern - WBS-Tarzow - SEE937857006797
  DatumLetzteAktualisierung: 2020-08-31T06:05:26.1054583 -> 2022-02-15T06:25:54.4267956
  GeplantesInbetriebnahmedatum: 2022-02-01 -> 2023-04-30
10 MW - operation - brandenburg - RRKW Feldheim - SEE976927444749
  NetzbetreiberpruefungDatum: 2021-10-28 -> 2022-03-03

2022-01

New projects (1):
10 MW - operation - thuringia - Batterie Breitenworbis - SEE977720016904

Updated projects (2):

12 MW - operation - bavaria - 70000000.00 - SEE940316838242
  DatumLetzteAktualisierung: 2021-10-30T04:41:59.5544412 -> 2021-12-16T16:44:50.4826401
  LokationMaStRNummer: SEL915124720911 -> SEL934186465974
  NetzbetreiberpruefungStatus: 0 -> 1
  NetzbetreiberpruefungDatum: 2021-10-30 -> 2021-12-16
11 MW - operation - lower saxony - Energiewende-Speicher - SEE935506652999
  NetzbetreiberpruefungDatum: 2020-09-23 -> 2021-12-28

2021-11

New projects (26):
72 MW - planning - nrw - Batteriespeicher Werne - SEE971932533266
66 MW - operation - brandenburg - Big Battery Lausitz - SEE905930139120
48 MW - operation - schleswig-holstein - BESS Jardelund - SEE999790559914
45 MW - planning - lower saxony - Batteriespeicher Emsland - SEE905843309764
18 MW - operation - bremen - Hybridregelkraftwerk - SEE913862454280
17 MW - operation - nrw - Q_ESS_Elverlingsen - SEE966091400436
16 MW - operation - bavaria - Hybridspeicher AU - SEE900291433160
16 MW - operation - saxony - BES BEN - SEE963081865633
16 MW - operation - saxony - BES GRO - SEE976362409624
15 MW - operation - saarland - GBS 2 KW Bexbach - SEE908096553144
15 MW - operation - saxony - Batteriespeicher Chemnitz GmbH & Co. KG - SEE910324388312
15 MW - operation - saarland - GBS KW Fenne - SEE919443669678
15 MW - operation - schleswig-holstein - Batteriespeicherkraftwerk - SEE933095868289
15 MW - operation - saarland - GBS KW Weiher - SEE941708872783
15 MW - operation - nrw - GBS KW Walsum - SEE964940893804
15 MW - operation - nrw - GBS KW Herne - SEE971138728251
15 MW - operation - saarland - GBS KW Bexbach - SEE990521990150
14 MW - operation - lower saxony - Batteriespeicher Herrenhausen - SEE953605889740
13 MW - planning - baden-wuerttemberg - Im Buckeberg 62 Stromspeicher - SEE946919525862
13 MW - planning - schleswig-holstein - Büttel Speicher - SEE984446277410
12 MW - operation - bavaria - 70000000.00 - SEE940316838242
11 MW - operation - nrw - Q_ESS_Luenen - SEE905490507995
11 MW - operation - lower saxony - Energiewende-Speicher - SEE935506652999
10 MW - operation - thuringia - SMAREG 1 - SEE931375347240
10 MW - planning - mecklenburg-vorpommern - WBS-Tarzow - SEE937857006797
10 MW - operation - brandenburg - RRKW Feldheim - SEE976927444749

Updated projects (0):