Swiftsure πŸ“β€οΈπŸ“ŠπŸ‘€πŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / new york / Staten Island
Dates
First heard 2021-01
Construction start
Operation start
Estimated start 2026-06
Construction time
Capacity in MWh
1300
πŸ“ This is an estimate
Maximum Power in MW
650
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Hecate Grid Swiftsure LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.602891+-74.178441
Coordinates
40.602891, -74.178441
πŸ“ Coords not known
Notes

Project website
https://www.hecateenergy.com/projects/
Sources
https://www.nyiso.com/documents/20142/1394430/NYISO-Interconnection-Queue-11-19-20.xlsx
Internal / External id
128 / 64235

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2021-01 report):

Plant Name / State
Swiftsure / NY
go live / power
2026-06 / 650MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
64235 / SWFTS
Entity name / entity id
Hecate Grid Swiftsure LLC / 63838
Changes:
2023-03
status_verbose: (L) Regulatory approvals pending. Not under construction -> (P) Planned for installation, but regulatory approvals not initiated
date: 2025-12 -> 2026-06 delayed by 6 months
2022-03
date: 2023-12 -> 2025-12 delayed by 24 months