Taos Mesa Energy Facility Hybrid πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / new mexico /
Dates
First heard |
2020-09 |
Construction start |
2022-05 |
Operation start |
2022-11 |
Estimated start |
2021-09 |
Construction time |
6 months -> 4 MWh/m
|
Capacity in MWh
24
π This is an estimate
Maximum Power in MW
12
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Taos Mesa Energy Facility, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:36.613442720802766+-103.73112992303248
Coordinates
36.613442720802766, -103.73112992303248
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
226 / 63728
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2023-02
report (Project first appeared in the
2020-09
report):
Plant Name / State
Taos Mesa Energy Facility Hybrid / NM
go live / power
2022-11 / 12MW
status / status verbose
operation / operation
Plant id / generator id
63728 / BESS
Entity name / entity id
Taos Mesa Energy Facility, LLC / 63420
Changes:
2023-01
status: construction -> operation πΎ π πΈ
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
2022-12
date: 2022-10 -> 2022-11 delayed by
1 month
2022-11
date: 2022-09 -> 2022-10 delayed by
1 month
2022-10
date: 2022-08 -> 2022-09 delayed by
1 month
2022-09
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
date: 2022-07 -> 2022-08 delayed by
1 month
2022-08
plant producer type: IPP -> Electric Utility
date: 2022-06 -> 2022-07 delayed by
1 month
2022-05
status: planning -> construction ποΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (V) Under construction, more than 50 percent complete
date: 2022-05 -> 2022-06 delayed by
1 month
2022-04
date: 2023-03 -> 2022-05 accelerated by
10 months
2021-11
date: 2021-09 -> 2023-03 delayed by
18 months
2021-10
status_verbose: (T) Regulatory approvals received. Not under construction -> (L) Regulatory approvals pending. Not under construction
2021-07
status_verbose: (L) Regulatory approvals pending. Not under construction -> (T) Regulatory approvals received. Not under construction