Arica Solar πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / california /
Dates
First heard |
2022-08 |
Construction start |
2022-10 |
Operation start |
2024-03 |
Estimated start |
2022-12 |
Construction time |
17 months -> 16 MWh/m
|
Capacity in MWh
272
π This is an estimate
Maximum Power in MW
136
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Arica Solar, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.005868576126275+-120.94054963684043
Coordinates
41.005868576126275, -120.94054963684043
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
699 / 65744
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2022-08
report):
Plant Name / State
Arica Solar / CA
go live / power
2024-03 / 136MW
status / status verbose
operation / operation
Plant id / generator id
65744 / ARCBA
Entity name / entity id
Arica Solar, LLC / 64996
Changes:
2024-05
status: construction -> operation πΎ π πΈ
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2023-10
date: 2023-12 -> 2024-03 delayed by
3 months
2023-09
date: 2023-11 -> 2023-12 delayed by
1 month
2023-06
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2023-02
date: 2023-12 -> 2023-11 accelerated by
1 month
2022-10
status: planning -> construction ποΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
date: 2022-12 -> 2023-12 delayed by
12 months