BES GRO π
Status
operation
Country / State / Closest City
π©πͺ germany / saxony /
Dates
First heard |
|
Construction start |
|
Operation start |
2019-07-18 |
Estimated start |
|
Construction time |
|
Capacity in MWh
25
Maximum Power in MW
16
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ BES Groitzsch GmbHοΌ Co. KG /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:51.140876+12.293085
Coordinates
51.140876, 12.293085
β
Coords are exact (+/- 50m)
Notes
Project website
Sources
https://www.marktstammdatenregister.de/MaStR/Einheit/Detail/IndexOeffentlich/2562905
Internal / External id
544 / SEE976362409624
DE MaStR data
The government data source for this battery is the DE Marktstammdatenregister (MaStR)
https://www.marktstammdatenregister.de/MaStR/
Info from the
2022-12
report
(Project first appeared in the
2021-11
report):
Plant Name / State
BES GRO / saxony
Go live / estimated go live
2019-07-18 /
MW
16
Status
operation
Changes: