BESS Jardelund πŸ“ŠπŸ‘€

Status
operation
Country / State / Closest City
πŸ‡©πŸ‡ͺ germany / schleswig-holstein / Jardelund
Dates
First heard
Construction start 2017-10-01
Operation start 2018-04-01
Estimated start
Construction time 6 months -> 8 MWh/m
Capacity in MWh
48
Maximum Power in MW
48
Manufacturer
NEC Energy Solutions (LG)
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ EnspireME /
Use case
frequency balancing
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:54.850889+9.194541
Coordinates
54.850889, 9.194541
βœ… Coords are exact (+/- 50m)
Notes
according to energy-storage.news, NEC Energy Solutions was acquired by LG Energy solutions in September 2021
Project website
https://www.neces.com/project/jardelund-germany-48-mw-51-mwh-2/
Sources
https://www.youtube.com/watch?v=UheTmGO7BN0
https://www.energy-storage.news/50mwh-battery-completed-in-germany-claims-europes-largest-crown/
https://www.marktstammdatenregister.de/MaStR/Einheit/Detail/IndexOeffentlich/3984077
Internal / External id
90 / SEE999790559914

DE MaStR data

The government data source for this battery is the DE Marktstammdatenregister (MaStR)
https://www.marktstammdatenregister.de/MaStR/
Info from the 2022-12 report (Project first appeared in the 2021-11 report):

Plant Name / State
BESS Jardelund / schleswig-holstein
Go live / estimated go live
2018-04-01 /
MW
48
Status
operation
Changes:
2022-12
NetzbetreiberpruefungDatum: 2021-02-12 -> 2022-11-11