Eccles Substation, Eccles - Battery Energy Storage System πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / scotland /
Dates
First heard 2023-06-15
Construction start
Operation start
Estimated start
Construction time
Capacity in MWh
50
πŸ“ This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Eccles Grid Stability Limited /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:55.666218+-2.308354
Coordinates
55.666218, -2.308354
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
930 / 13003

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-01 report (Project first appeared in the 2023-01 report):

Plant Name / State
Eccles Substation, Eccles - Battery Energy Storage System / scotland
Go live / estimated go live
/
MW
50
Status
planning
Changes:
2023-07
Record Last Updated (dd/mm/yyyy): 12/01/2023 -> 30/06/2023
Development Status: Planning Application Submitted -> Planning Permission Granted
Development Status (short): Application Submitted -> Awaiting Construction
Planning Permission Granted: -> 15/06/2023
Planning Permission Expired: -> 15/06/2028