Mardyck 👤

Status
operation
Country / State / Closest City
🇫🇷 france / / Dunkirk
Dates
First heard
Construction start 2020-10-01
Operation start 2021-02-01
Estimated start
Construction time 4 months -> 6 MWh/m
Capacity in MWh
25
Maximum Power in MW
25
Manufacturer
Saft
Type / Number of Packs / Cells
Intensium Max 20 High Energy (20ft container) / 11 / NMC
Customer / Owner / Developer
RTE / Total /
Use case
frequency balancing
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:51.029549+2.252929
Coordinates
51.029549, 2.252929
✅ The site is known, coords are +/- 1 kilometer
Notes
saft is owned by total
Project website
Sources
https://www.energy-storage.news/frances-biggest-battery-storage-system-at-25mw-goes-into-operation/
https://totalenergies.com/media/news/press-releases/total-build-largest-battery-based-energy-storage-project-france
https://www.saftbatteries.com/products-solutions/products/intensium�-max-20-high-energy
Internal / External id
93 /