Derehams Farm, Derehams Lane - Battery Storage ππ
Status
construction
Country / State / Closest City
π¬π§ uk / south east /
Dates
First heard |
2022-12-12 |
Construction start |
2024-02-19 |
Operation start |
|
Estimated start |
|
Construction time |
|
Capacity in MWh
40
π This is an estimate
Maximum Power in MW
40
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Eku Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:51.611399+-0.693977
Coordinates
51.611399, -0.693977
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
912 / 12803
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report
(Project first appeared in the
2023-01
report):
Plant Name / State
Derehams Farm, Derehams Lane - Battery Storage / south east
Go live / estimated go live
/
MW
40
Status
construction
Changes:
2024-04
Record Last Updated (dd/mm/yyyy): 12/07/2023 -> 22/02/2024
Operator (or Applicant): Capbal Limited -> Eku Energy
Development Status: Planning Permission Granted -> Under Construction
Development Status (short): Awaiting Construction -> Under Construction
Planning Permission Refused: -> 29/06/2023
Under Construction: -> 19/02/2024
status: planning -> construction ποΈ
2023-07
Record Last Updated (dd/mm/yyyy): 12/12/2022 -> 12/07/2023
Development Status: Planning Application Submitted -> Planning Permission Granted
Development Status (short): Application Submitted -> Awaiting Construction
Planning Authority: Buckinghamshire Council -> Buckinghamshire Council - Wycombe Area
Planning Permission Granted: -> 29/06/2023
Planning Permission Expired: -> 29/06/2026