National Grid Electricity Substation, Capenhurst Lane - Battery Storage πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / north west /
Dates
First heard 2022-11-28
Construction start 2021-06-01
Operation start 2023-02-14
Estimated start
Construction time 20 months -> 5 MWh/m
Capacity in MWh
100
πŸ“ This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Zenobe Energy Limited /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:53.256874+-2.95341
Coordinates
53.256874, -2.95341
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
905 / 12725

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-04 report (Project first appeared in the 2023-01 report):

Plant Name / State
National Grid Electricity Substation, Capenhurst Lane - Battery Storage / north west
Go live / estimated go live
2023-02-14 /
MW
100
Status
operation
Changes:
2024-04
Planning Authority: Cheshire West and Chester Council -> Cheshire West & Chester Council
Planning Permission Refused: -> 01/02/2021

2024-01
Planning Authority: Cheshire West & Chester Council -> Cheshire West and Chester Council
Operational: 11/02/2023 ->

2023-07
Record Last Updated (dd/mm/yyyy): 28/11/2022 -> 14/02/2023
Development Status: Under Construction -> Operational
Development Status (short): Under Construction -> Operational
Planning Permission Expired: 01/02/2024 -> 01/06/2021
Under Construction: 01/06/2021 ->
Operational: -> 11/02/2023
status: construction -> operation 🍾 πŸŽ‰ 🍸