National Grid Electricity Substation, Capenhurst Lane - Battery Storage ππ
Status
operation
Country / State / Closest City
π¬π§ uk / north west /
Dates
First heard |
2022-11-28 |
Construction start |
2021-06-01 |
Operation start |
2023-02-14 |
Estimated start |
|
Construction time |
20 months -> 5 MWh/m
|
Capacity in MWh
100
π This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Zenobe Energy Limited /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:53.256874+-2.95341
Coordinates
53.256874, -2.95341
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
905 / 12725
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report
(Project first appeared in the
2023-01
report):
Plant Name / State
National Grid Electricity Substation, Capenhurst Lane - Battery Storage / north west
Go live / estimated go live
2023-02-14 /
MW
100
Status
operation
Changes:
2024-04
Planning Authority: Cheshire West and Chester Council -> Cheshire West & Chester Council
Planning Permission Refused: -> 01/02/2021
2024-01
Planning Authority: Cheshire West & Chester Council -> Cheshire West and Chester Council
Operational: 11/02/2023 ->
2023-07
Record Last Updated (dd/mm/yyyy): 28/11/2022 -> 14/02/2023
Development Status: Under Construction -> Operational
Development Status (short): Under Construction -> Operational
Planning Permission Expired: 01/02/2024 -> 01/06/2021
Under Construction: 01/06/2021 ->
Operational: -> 11/02/2023
status: construction -> operation πΎ π πΈ