Eggborough Power Station, Selby Road - Battery Storage πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / yorkshire and humber /
Dates
First heard 2023-01-17
Construction start
Operation start
Estimated start
Construction time
Capacity in MWh
500
πŸ“ This is an estimate
Maximum Power in MW
500
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Eggborough Power Limited /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:53.713432+-1.129813
Coordinates
53.713432, -1.129813
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
893 / 12483

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-04 report (Project first appeared in the 2023-01 report):

Plant Name / State
Eggborough Power Station, Selby Road - Battery Storage / yorkshire and humber
Go live / estimated go live
/
MW
500
Status
planning
Changes:
2023-07
Record Last Updated (dd/mm/yyyy): 31/10/2022 -> 24/01/2023
Development Status: Planning Application Submitted -> Planning Permission Granted
Development Status (short): Application Submitted -> Awaiting Construction
Planning Permission Granted: -> 17/01/2023
Planning Permission Expired: -> 17/01/2026