Newmarket Road, Bottisham - Battery Energy Storage ππ
Status
planning
Country / State / Closest City
π¬π§ uk / eastern /
Dates
First heard |
2023-12-21 |
Construction start |
|
Operation start |
|
Estimated start |
|
Construction time |
|
Capacity in MWh
50
π This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Ridge Clean Energy Limited /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:52.21614+0.282934
Coordinates
52.21614, 0.282934
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
874 / 10486
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report
(Project first appeared in the
2023-01
report):
Plant Name / State
Newmarket Road, Bottisham - Battery Energy Storage / eastern
Go live / estimated go live
/
MW
50
Status
planning
Changes:
2024-04
Record Last Updated (dd/mm/yyyy): 03/01/2024 ->
2024-01
Record Last Updated (dd/mm/yyyy): 01/12/2022 -> 03/01/2024
Development Status: Planning Application Submitted -> Planning Permission Granted
Development Status (short): Application Submitted -> Awaiting Construction
Planning Permission Expired: -> 21/12/2026