Welkin Mill ππ
Status
planning
Country / State / Closest City
π¬π§ uk / north west /
Dates
First heard |
2023-01-05 |
Construction start |
|
Operation start |
|
Estimated start |
|
Construction time |
|
Capacity in MWh
49
π This is an estimate
Maximum Power in MW
49
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Noriker Power /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:53.419099+-2.135741
Coordinates
53.419099, -2.135741
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
871 / 7832
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report
(Project first appeared in the
2023-01
report):
Plant Name / State
Welkin Mill / north west
Go live / estimated go live
/
MW
49
Status
planning
Changes:
2024-01