Househill House, Househill - Battery Storage πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / scotland /
Dates
First heard 2023-02-15
Construction start
Operation start
Estimated start
Construction time
Capacity in MWh
49
πŸ“ This is an estimate
Maximum Power in MW
49
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Whirlwind Energy Storage Limited /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:57.575557+-3.861558
Coordinates
57.575557, -3.861558
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
830 / 12056

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-01 report (Project first appeared in the 2022-10 report):

Plant Name / State
Househill House, Househill - Battery Storage / scotland
Go live / estimated go live
/
MW
49
Status
planning
Changes:
2024-01
Planning Authority: Highlands Council -> Highland Council

2023-07
Record Last Updated (dd/mm/yyyy): 09/09/2022 -> 10/03/2023
Development Status: Planning Application Submitted -> Planning Permission Granted
Development Status (short): Application Submitted -> Awaiting Construction
Planning Permission Granted: -> 15/02/2023
Planning Permission Expired: -> 15/02/2026

2023-01
County: Highlands -> Highland