Says Court Farm, Coalpit Heath - Battery Energy Storage πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / south west /
Dates
First heard 2022-11-02
Construction start
Operation start
Estimated start
Construction time
Capacity in MWh
50
πŸ“ This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Anglo Renewables Limited /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:51.533595+-2.449525
Coordinates
51.533595, -2.449525
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
823 / 11793

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-04 report (Project first appeared in the 2022-10 report):

Plant Name / State
Says Court Farm, Coalpit Heath - Battery Energy Storage / south west
Go live / estimated go live
/
MW
50
Status
planning
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): 14/11/2022 -> 04/08/2022

2023-01
Record Last Updated (dd/mm/yyyy): 04/08/2022 -> 14/11/2022
Development Status: Planning Application Submitted -> Planning Permission Granted
Development Status (short): Application Submitted -> Awaiting Construction
Planning Permission Granted: -> 02/11/2022
Planning Permission Expired: -> 02/11/2025