High Road, Saddlebow - Battery Storage ππ
Status
cancelled
Country / State / Closest City
π¬π§ uk / eastern /
Dates
First heard |
2022-07-15 |
Construction start |
|
Operation start |
|
Estimated start |
|
Month disappeared |
2023-07 |
Construction time |
|
Capacity in MWh
50
π This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Lynn Power Limited /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:52.724763+0.379761
Coordinates
52.724763, 0.379761
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
816 / 11648
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2023-01
report
(Project first appeared in the
2022-10
report):
Plant Name / State
High Road, Saddlebow - Battery Storage / eastern
Go live / estimated go live
/
MW
50
Status
cancelled
Changes:
2023-01
Record Last Updated (dd/mm/yyyy): 15/07/2022 -> 04/11/2022
2023-07
This project disappeared in the
2023-07
report.
That's why the status was set to
cancelled