Worset Lane - Battery Energy Storage System πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / north east /
Dates
First heard 2023-01-18
Construction start
Operation start
Estimated start
Construction time
Capacity in MWh
200
πŸ“ This is an estimate
Maximum Power in MW
200
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Clearstone Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:54.685388+-1.212911
Coordinates
54.685388, -1.212911
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
811 / 11406

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-01 report (Project first appeared in the 2022-10 report):

Plant Name / State
Worset Lane - Battery Energy Storage System / north east
Go live / estimated go live
/
MW
200
Status
planning
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): 01/02/2023 -> 07/06/2022

2023-07
Record Last Updated (dd/mm/yyyy): 05/08/2022 -> 01/02/2023
Development Status: Planning Application Submitted -> Planning Permission Granted
Development Status (short): Application Submitted -> Awaiting Construction
Planning Permission Granted: -> 18/01/2023
Planning Permission Expired: -> 18/01/2026