Ochiltree - Battery Sorage πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / scotland /
Dates
First heard 2022-10-05
Construction start
Operation start
Estimated start
Construction time
Capacity in MWh
19
πŸ“ This is an estimate
Maximum Power in MW
19
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Statkraft UK Limited /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:55.454634+-4.266842
Coordinates
55.454634, -4.266842
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
805 / 10162

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-01 report (Project first appeared in the 2022-10 report):

Plant Name / State
Ochiltree - Battery Sorage / scotland
Go live / estimated go live
/
MW
19
Status
planning
Changes:
2024-01
Development Status: Planning Permission Granted -> Revised
Development Status (short): Awaiting Construction -> Revised
Are they re-applying (New REPD Ref): -> 15312

2023-07
Planning Permission Expired: 05/10/2022 -> 05/10/2025

2023-01
Y-coordinate: 62020 -> 620201
lat: 50.440496 -> 55.454634
long: -4.018763 -> -4.266842