Kilmarnock South Substation - Battery storage ππ
Status
construction
Country / State / Closest City
π¬π§ uk / scotland /
Dates
First heard |
2022-02-14 |
Construction start |
2024-01-26 |
Operation start |
|
Estimated start |
|
Construction time |
|
Capacity in MWh
300
π This is an estimate
Maximum Power in MW
300
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Zenobe Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:55.578171+-4.46746
Coordinates
55.578171, -4.46746
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
803 / 9696
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report
(Project first appeared in the
2022-10
report):
Plant Name / State
Kilmarnock South Substation - Battery storage / scotland
Go live / estimated go live
/
MW
300
Status
construction
Changes:
2024-04
Record Last Updated (dd/mm/yyyy): 27/09/2021 ->
Development Status: Planning Permission Granted -> Under Construction
Development Status (short): Awaiting Construction -> Under Construction
Under Construction: -> 26/01/2024
status: planning -> construction ποΈ
2024-01
Record Last Updated (dd/mm/yyyy): 14/02/2022 -> 27/09/2021
Development Status: Planning Application Submitted -> Planning Permission Granted
Development Status (short): Application Submitted -> Awaiting Construction
Planning Application Submitted: 01/04/2022 -> 22/02/2022
Planning Permission Expired: -> 10/03/2028