Norrington Gate Farm, Broughton Gifford - Battery Energy Storage Facility πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / south west /
Dates
First heard 2023-01-06
Construction start
Operation start
Estimated start
Construction time
Capacity in MWh
150
πŸ“ This is an estimate
Maximum Power in MW
150
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ ADV 003 Limited /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:51.375577+-2.171149
Coordinates
51.375577, -2.171149
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
770 / 11612

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-01 report (Project first appeared in the 2022-07 report):

Plant Name / State
Norrington Gate Farm, Broughton Gifford - Battery Energy Storage Facility / south west
Go live / estimated go live
/
MW
150
Status
planning
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): 23/01/2023 -> 08/07/2022

2023-07
Record Last Updated (dd/mm/yyyy): 17/10/2022 -> 23/01/2023
Development Status: Planning Application Submitted -> Planning Permission Granted
Development Status (short): Application Submitted -> Awaiting Construction
Planning Permission Granted: -> 06/01/2023
Planning Permission Expired: -> 06/01/2026

2023-01
Record Last Updated (dd/mm/yyyy): 08/07/2022 -> 17/10/2022