Maybrook Road - Battery facility ππ
Status
planning
Country / State / Closest City
π¬π§ uk / west midlands /
Dates
First heard |
2022-08-08 |
Construction start |
|
Operation start |
|
Estimated start |
|
Construction time |
|
Capacity in MWh
13
π This is an estimate
Maximum Power in MW
13
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Conrad Energy (Develeopments) Limited /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:52.529587+-1.788339
Coordinates
52.529587, -1.788339
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
744 / 11008
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report
(Project first appeared in the
2022-07
report):
Plant Name / State
Maybrook Road - Battery facility / west midlands
Go live / estimated go live
/
MW
13
Status
planning
Changes:
2024-04
Record Last Updated (dd/mm/yyyy): 19/04/2022 ->
Planning Permission Expired: NA ->
2024-01
Record Last Updated (dd/mm/yyyy): 18/08/2022 -> 19/04/2022
2023-07
Planning Permission Expired: -> NA
2022-10
Record Last Updated (dd/mm/yyyy): 19/04/2022 -> 18/08/2022
Development Status: Planning Application Submitted -> Planning Permission Granted
Development Status (short): Application Submitted -> Awaiting Construction
Planning Permission Granted: -> 08/08/2022