Grendon Lakes, Grendon - Battery Storage Facility ππ
Status
planning
Country / State / Closest City
π¬π§ uk / east midlands /
Dates
First heard |
2022-04-06 |
Construction start |
|
Operation start |
|
Estimated start |
|
Construction time |
|
Capacity in MWh
49
π This is an estimate
Maximum Power in MW
49
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Statera Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:52.244024+-0.722824
Coordinates
52.244024, -0.722824
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
675 / 10955
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report
(Project first appeared in the
2024-01
report):
Plant Name / State
Grendon Lakes, Grendon - Battery Storage Facility / east midlands
Go live / estimated go live
/
MW
49
Status
planning
Changes:
2024-04
Record Last Updated (dd/mm/yyyy): 06/04/2022 ->
Are they re-applying (New REPD Ref): 14321 ->
Are they re-applying (Old REPD Ref) : 9341 ->