Vause Farm - Battery Storage ππ
Status
planning
Country / State / Closest City
π¬π§ uk / north west /
Dates
First heard |
2024-02-09 |
Construction start |
|
Operation start |
|
Estimated start |
|
Construction time |
|
Capacity in MWh
20
π This is an estimate
Maximum Power in MW
20
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Sirius Renewable Energy Limited /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:53.614427+-2.688388
Coordinates
53.614427, -2.688388
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
636 / 10989
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report
(Project first appeared in the
2022-04
report):
Plant Name / State
Vause Farm - Battery Storage / north west
Go live / estimated go live
/
MW
20
Status
planning
Changes:
2024-04
Record Last Updated (dd/mm/yyyy): 11/04/2022 ->
Development Status: Planning Application Submitted -> Planning Permission Granted
Development Status (short): Application Submitted -> Awaiting Construction
Planning Permission Expired: -> 09/02/2027