A981 Fraserburgh - Battery Energy Storage ππ
Status
planning
Country / State / Closest City
π¬π§ uk / scotland /
Dates
First heard |
2022-02-21 |
Construction start |
|
Operation start |
|
Estimated start |
|
Construction time |
|
Capacity in MWh
25
π This is an estimate
Maximum Power in MW
25
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Fraserburgh Energy Limited /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:57.671398+-2.026323
Coordinates
57.671398, -2.026323
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
606 / 10222
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report
(Project first appeared in the
2021-12
report):
Plant Name / State
A981 Fraserburgh - Battery Energy Storage / scotland
Go live / estimated go live
/
MW
25
Status
planning
Changes:
2024-04
Record Last Updated (dd/mm/yyyy): 28/02/2022 ->
2022-10
Planning Permission Expired: -> 21/02/2025
2022-04
Record Last Updated (dd/mm/yyyy): 29/12/2021 -> 28/02/2022
Development Status: Planning Application Submitted -> Planning Permission Granted
Development Status (short): Application Submitted -> Awaiting Construction
Planning Permission Granted: -> 21/02/2022