Astra Centre, Royal Barn Road - Energy Storage ππ
Status
construction
Country / State / Closest City
π¬π§ uk / north west /
Dates
First heard |
2021-09-13 |
Construction start |
2024-02-27 |
Operation start |
|
Estimated start |
|
Construction time |
|
Capacity in MWh
40
π This is an estimate
Maximum Power in MW
40
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Arlington Energy Limited /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:53.596617+-2.178949
Coordinates
53.596617, -2.178949
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
514 / 9584
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report
(Project first appeared in the
2021-09
report):
Plant Name / State
Astra Centre, Royal Barn Road - Energy Storage / north west
Go live / estimated go live
/
MW
40
Status
construction
Changes:
2024-04
Record Last Updated (dd/mm/yyyy): 05/07/2023 ->
Development Status: Planning Permission Granted -> Under Construction
Development Status (short): Awaiting Construction -> Under Construction
Under Construction: -> 27/02/2024
status: planning -> construction ποΈ
2023-07
Record Last Updated (dd/mm/yyyy): 24/02/2022 -> 05/07/2023
2022-10
Planning Permission Expired: -> 10/02/2025
2022-04
Record Last Updated (dd/mm/yyyy): 13/09/2021 -> 24/02/2022
Development Status: Planning Application Submitted -> Planning Permission Granted
Development Status (short): Application Submitted -> Awaiting Construction
Planning Permission Granted: -> 10/02/2022
2021-12
Planning Authority: Rochdale borough Council -> Rochdale Borough Council