Caldwell Road - Battery Storage ππ
Status
planning
Country / State / Closest City
π¬π§ uk / east midlands /
Dates
First heard |
2022-03-03 |
Construction start |
|
Operation start |
|
Estimated start |
|
Construction time |
|
Capacity in MWh
90
π This is an estimate
Maximum Power in MW
90
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Infrared Capital Partners Limited /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:52.768556+-1.626224
Coordinates
52.768556, -1.626224
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
508 / 9507
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report
(Project first appeared in the
2021-09
report):
Plant Name / State
Caldwell Road - Battery Storage / east midlands
Go live / estimated go live
/
MW
90
Status
planning
Changes:
2024-04
Record Last Updated (dd/mm/yyyy): 04/11/2022 ->
2023-01
Record Last Updated (dd/mm/yyyy): 19/04/2022 -> 04/11/2022
Operator (or Applicant): Aura Power BESS Ltd -> Infrared Capital Partners Limited
2022-10
Planning Permission Expired: -> 03/03/2025
2022-07
Record Last Updated (dd/mm/yyyy): 31/08/2021 -> 19/04/2022
Development Status: Planning Application Submitted -> Planning Permission Granted
Development Status (short): Application Submitted -> Awaiting Construction
Planning Permission Granted: -> 03/03/2022