South Farm Solar Park πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / south west /
Dates
First heard 2021-07-28
Construction start 2021-01-07
Operation start 2022-12-21
Estimated start
Construction time 23 months -> 0 MWh/m
Capacity in MWh
10
πŸ“ This is an estimate
Maximum Power in MW
10
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Voltalia UK /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:50.813188+-2.141475
Coordinates
50.813188, -2.141475
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
502 / 9361

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-04 report (Project first appeared in the 2021-09 report):

Plant Name / State
South Farm Solar Park / south west
Go live / estimated go live
2022-12-21 /
MW
10
Status
operation
Changes:
2024-01
Operational: 16/12/2022 ->

2023-01
Record Last Updated (dd/mm/yyyy): 28/07/2021 -> 21/12/2022
Development Status: Under Construction -> Operational
Development Status (short): Under Construction -> Operational
Operational: -> 16/12/2022
status: construction -> operation 🍾 πŸŽ‰ 🍸