Maelor Gasworks - Solar Farm & Battery Storage πŸ“ŠπŸ“

Status
cancelled
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / wales /
Dates
First heard 2021-07-22
Construction start
Operation start
Estimated start
Month disappeared 2023-01
Construction time
Capacity in MWh
16
πŸ“ This is an estimate
Maximum Power in MW
16
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Novus Renewable Services Limited /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:53.026889+-2.924234
Coordinates
53.026889, -2.924234
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
500 / 9343

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2022-10 report (Project first appeared in the 2021-09 report):

Plant Name / State
Maelor Gasworks - Solar Farm & Battery Storage / wales
Go live / estimated go live
/
MW
16
Status
cancelled
Changes:

2023-01 This project disappeared in the 2023-01 report.
That's why the status was set to cancelled